Kıyıköy Wind Power Plant

Project Details

Project Type Design – Build
Project Location Tekirdağ, TURKEY
Owner Beşiktepe Enerji Üretim ve Ticaret A.Ş.
Project Start 1 September 2014
Project End 1 November 2015

Key Project Quantities:

  • 15 x Nordex N117/3000 kW
  • 15 x 3 MW = 45 MWm/44 MWe
  • 62,5/50 MVA Transformer Substation
  • Production : 170.800.000 kWh ( P50 )
  • Capacity factor : %44
  • 13 km access roads
  • 36 km underground MV cable
  • 25 km F/O cable